Engineering Projects
Current City Improvement Projects

Manhole Lining 2018
Under construction.  Installing an approved manhole lining system on approx. 270 existing  brick manholes.

Juniper Drive Booster Pump
Construction starts next week.  Installing a new City furnished booster pump and motor, new flow meter, and associated piping.  Completely upgrade the electrical and controls.  Rebuilding roof on existing building. 

Combined Storage Facilities 2018
Awarded, contractor getting designs and submittals approved.  The project includes construction of the following items: covered 80-foot by 100-foot Combined Storage Facility with concrete slab at the Operations Complex, mezzanine in Building 5 at the COF, 20-foot by 50-foot addition to match existing at Building 5 of the COF, an automatic lift gate and controls for Fire Station No. 1, a 35-foot by 80.5-foot carport attached to Building 1 at the Operations Complex. Associated work includes engineered designs for all structures, geotechnical reports if needed for the permits, plan preparation, permits, site preparation, fencing, concrete, HMA, electrical, insulation, overhead doors, heating.

Street Light Rehab Project 2018
Starts after Thanksgiving.  The work shall include retrofitting an existing metered street light system on Owen Road, Loring Drive, and Westover Boulevard that is maintained by the City of Moses Lake, into a non-metered street light system that will be owned and maintained by Grant County PUD.

Water meter vault project 2018
Just finished last week. This project includes the replacement of eight (8) 3-inch diameter water meter and vaults, two (2) 1  ½” diameter water meter and tiles, and one (1) 2-inch water meter and tile and associated piping within the City of Moses Lake water service area.  The work includes cement concrete work (sidewalk, water meter pads, and curb), HMA patching, repair of disturbed irrigation systems, and sod replacement.