Estimated Project Cost: $40,000 to $80,000 Contract Working Days: 20
This project consists of the restoration of an existing concrete bottom sedimentation pond located at the City’s Larson Wastewater Treatment Facility at 6691 Randolph Rd NE, Moses Lake, WA. Concrete joints and random cracks will be prepared for sealing, filled, and finish sealed with the approved concrete crack and joint sealing system. A third-party inspection service will be required to complete inspections and submit reports.
|
|
12/1/2022 8:00 AM
|
|
Columbia Basin Herald, MRSC
|
|
Open Until Contracted
|
|
Bid Opening January 12, 2023, at 2:00 PM
|
|
321 S Balsam St, Moses Lake WA
|
|
Mark Beaulieu, P.E.; 509.764.3776; mbeaulieu@cityofml.com
|
|
$50.00 for paper copy
|
|
Plans and specifications shall be obtained via the Civic Center Annex at 321 S Balsam St, Moses Lake WA 98837
|
|
8:00 a.m. to 4:00 p.m.
|
|
Attached as a related document, call to request, (509)764-3786, or email request to tkehret@cityofml.com
|
|
All bids shall be received before said opening time in sealed envelopes with LARSON SEDIMENTATION POND REHABILITATION marked plainly thereon. All bids shall be accompanied by a deposit in the form of a postal money order, cashier's check, or bond in an amount equal to 5 percent of the maximum total of the bid. Only bids from bidders who have received plans and specifications VIA the Civic Center Annex will be accepted. Copies of plans and specifications are on file for review at the cityofml.com Engineering projects website.
|
|
|